PETS III Flyer: WASH Key Findings

[rank_math_breadcrumb]

Nearly 15 months after their provisional acceptance, 11% of the projects have not been definitively accepted.

77% of WASH projects carried out in 2017 started late.

The average time taken by the financial controller to process a file is 18 days (out of the 72 hours prescribed).
64% of commitment files processed by financial controllers were processed after the deadline.